This site has a primary cooling water system from an existing 20 year old cooling tower.
The plant required a substantial upgrade of the furnace plant & cooling equipment due to blocked pipework – caused by poor quality water and incorrect /irregular water treatment.
The project was completed on site within a very tight time frame requiring around the clock working to renew all of the existing mild steel distribution pipework and replace with new stainless steel pipework along with an extension for additional furnace plant to be added at a later date.
Significant challenging factors relating to this project were the high level nature of the work coupled with strict observed shut down periods to limit plant down time and minimise the disruption in service.
Our experience in fabrication, installation, heavy lifting, working at height and programme adherence were all called to the fore to ensure success.